Construction & Pre-Commissioning Integration

Readiness, interface, constraint, inspection, testing and system/subsystem turnover management connecting Construction, QC, Client/PMT, Pre-Commissioning and Completion.

Summary

6Tracked Tags
92%Construction
67%QC Ready
25%Pre-Com
4RFI Ready
2Blocked
3Constraints
0Turnover Ready

Integrated Workflow

Construction→Internal QC→RFI / Client→IMM→Pre-Commissioning→System Readiness→CMS

Construction Readiness

TagDisciplineEquipmentSystemSubsystemInstallationSupportCoatingIFCInternal QC%Status
408-3J-PC-00801ElectricalCableSYS-240SUB-240-E01CompleteCompleteN/ACurrentComplete100%Ready
408-3J-PC-00803ElectricalCableSYS-240SUB-240-E01RectificationCompleteN/ACurrentPending85%Blocked
408-3M-CTR-0011ElectricalCable TraySYS-245SUB-245-E02IncompleteIncompletePendingUnder ReviewPending65%Blocked
408-3I-SC-00101InstrumentationCableSYS-216SUB-216-I01CompleteCompleteN/ACurrentComplete100%Ready

Interdiscipline Interface Management

IDArea/TagFromInterfacing DisciplineIssueResponsibleTargetImpactStatus
INT-001PDM 216/221 Cable TrayElectricalStructuralSupport modification/location requires interdisciplinary verification.Field Engineering / Structural2026-09-14Rework / ScheduleOpen
INT-002Equipment SupportsE&ICoatingCoating clearance required before final installation RFI.Coating Construction / QC2026-09-12RFI ReadinessIn Progress
INT-003Motor Solo RunElectricalMechanicalAlignment/uncoupling coordination before solo run.Mechanical / Pre-Com2026-09-16Pre-CommissioningOpen

Inspection / RFI Readiness Gate

Checks construction, internal QC, ITP prerequisites, controlled documents, NCR/punch status and calibration validity.

Pre-Commissioning Activities

TagSystemActivityPrerequisiteProcedureVendorRFIResultStatus
408-3J-PC-00801SYS-240IR & ContinuityCable installation acceptedPC-E-CBL-001NoYesPassedCompleted
408-3L-BC-0006SYS-245Battery Charger SATInstallation + approved SAT procedureSAT-BC-006YesYesPendingConstraint
KM-1411ASYS-240Motor Solo RunElectrical tests + mechanical readinessPC-MTR-001As RequiredYesPendingInterface Pending

Constraints & Interface Register

IDArea/TagCategoryDescriptionOwnerTargetImpactRiskStatus
CON-001408-3M-CTR-0011ConstructionCable tray support incomplete.Construction2026-09-13RFI / Cable PullingHighOpen
CON-002408-3L-BC-0006Vendor / ProcedureVendor/SAT readiness and approved procedure required.Pre-Com2026-09-15SAT / EnergizationHighOpen
CON-003PDM 216/221Engineering InterfaceSupport modification requires structural/field engineering resolution.Field Engineering2026-09-14Rework / ScheduleMediumIn Progress

System / Subsystem Readiness

SystemSubsystemDisciplineConstructionInspection/ITRNCRPunchPre-ComOverallReadiness
SYS-240SUB-240-E01Electrical98%92%1 Open3 B88%91%Conditional
SYS-245SUB-245-E01Electrical94%87%0 Blocking5 B72%84%Not Ready
SYS-216SUB-216-I01Instrumentation96%90%0 Blocking2 B81%89%Conditional
Blocking NCRs, Category A punches, mandatory incomplete tests or unresolved prerequisites can prevent turnover regardless of percentage.

Turnover to Completion Management System

Eligibility uses construction, accepted inspection/ITR, quality, punch, pre-commissioning and dossier criteria.